I’ve found that one of the hardest things for people to wrap their heads around when talking about the feasibility of a project is the question of how long that project is going to take. We want it to be a simple mathematic algorithm: we have x number of people working y number of hours and each unit will take z hours to complete; if we multiply x times y, we’ll get the number of “person hours” we have available, and we can compare that to the sum of the z hours required for each of the units (x times y = z). Unfortunately, the picture is much more complex than that simple equation: some tasks may require specific skill sets to complete, which not all employees have; some tasks can be completed more quickly by adding additional labor while others will take longer; resources like tool availability limit how much can be accomplished at any given time; certain tasks must be completed before others can begin; the list can go on and on.
Over the past two weeks we’ve looked at two methods that can help shed light on these complexities: the work breakdown structure and the PERT chart. The work breakdown structure (WBS) is, in many ways, the most fundamental tool in our arsenal for visualizing and understanding time; a WBS represents every project down into a series of the smallest elements—sometimes called “deliverables”—that can be quantified in terms of resources and time required for completion. On the one hand, the WBS provides only a crude measure of the time required to complete a project (analogous to the equation above), but on the other, it provides a huge amount of raw data that can be manipulated to incorporate the myriad complexities a scheduling a project must tackle.
A PERT chart builds upon the work breakdown structure to develop a picture of how the relationships amongst elements determine when they might be completed. A PERT chart will make it clear which deliverables must be finished before others can be started, and which deliverables can be started without waiting for any others to be completed. The resulting maps create a clear picture of what parts of the project can be undertaken concurrently, and which might have to wait until later in the process.
One thing we haven’t done with our PERT chart yet, however, is deal specifically with time—while so far we’ve used it to illuminate the relationships between start and completion of elements of a project, we’ve not looked at how a PERT chart, and a related tool, the critical path method (CPM) can demonstrate how long each element of a project, and, by extension the entire project, will take. That is the focus of this week’s post: duration and the critical path.
Remember the PERT chart node we looked at last week? (It’s also at right, if you don’t.) That node includes a space to indicate the estimated duration of a task, as well as spaces for four somewhat confusing pieces of information: “early start,” “early finish,” “late start,” and “late finish.” These five pieces, when taken together and combined with the relational information the PERT chart provides, can give us a pretty good measure of when things might be able to happen (or have to happen) in our schedule.
Consider the project, “getting ready for work in the morning.” The WBS for that project might look like this (note that it’s still a little cold where I am in the mornings, and some days I have to start my car a little before I leave!):
1. Hygiene routine
1.1 Brush Teeth
1.2 Shower
1.2.1 Shampoo
1.2.2 Wash
2. Get Dressed
2.1 Iron shirt
2.2 Put on clothes
2.3 Put on tie
3. Breakfast
3.1 Cook Toast
3.2 Pour cereal and milk
3.3 Eat
3.4 Clean Dishes
4. Warm up car
5. Leave for work
Each of these elements has a particular length of time it will take to complete; it may take five minutes to brush your teeth, five to shampoo, five more to wash your body, etc., etc. This information would be recorded in the “duration” field in the PERT chart node.
The whole project “getting ready for work” is bounded by two milestones (or key date/time considerations): the time the alarm is set for—say, 7:00 am—and the latest time we need to leave to get to work on time—say, 8:30 am. After building the PERT chart and organizing each of the above elements according to their start-finish relationships to each other, we can begin to consider when is the earliest each of these elements can start, and based on that start time, when is the earliest each can be completed? We do this by working forward through the chart, beginning with the milestone of 7:00 am.
The “early start” time for each node cannot be any sooner than the latest “early finish” time of all predecessor nodes. For example, the node “clean dishes,” must be preceded by the node “eat” (otherwise there are no dishes to clean!). The earliest start time for “clean dishes” would be the same time as the earliest completion time for the node “eat.” The image below shows one possible PERT chart for the above WBS, with duration, early start and early finish times.
According to the PERT chart, if we were incredibly efficient in our allocation of labor, we should be able to get out the door by 7:35 am, almost one hour before our required departure time of 8:30!
(“Hang on a minute,” you say? You’re right. It would be physically impossible for me to brush my teeth, iron my shirt, cook my toast, and pour my milk and cereal all at the same time, and the PERT chart does seem to suggest that’s something I’ll have to do to get out the door by 7:35. There are two things to keep in mind, however: first, we’re not done with this chart—this data is only part of the whole picture. Second, this chart doesn’t take into consideration available labor resources; one set of resources might be a list made up of me, myself, and I, but another may include myself, my wife, who could perhaps iron my shirt while I brushed my teeth, and my son, who could drop the toast in the toaster while all this is going on.)
Late to Rise
Now, proceed backwards from the final early finish time, 7:35; the late finish for each node will be based on the late start of all successor nodes, as shown in the image below:
These “late” times must be considered in conjunction with the “early” times. When you consider them together, the last—and in some ways the most revealing—field in the PERT node box can be filled in: the “slack” node. This is the amount of time there is between the early and late start times, and represents how far the start time can shift according to resource availability and other outside influences.
Slacker!
Slack time is important because in every project, there will be a sequence of nodes in the PERT chart which have the least slack time. It is this sequence of nodes that we refer to as the “critical path.” These nodes, from start to finish, represent the shortest amount of time that the project can take to complete.
In our example, there are actually two critical paths (which is not uncommon):
Wake up -> Cook Toast -> Eat Breakfast -> Clean Dishes -> Put on Tie -> Leave for work
Wake up -> Pour Cereal/Milk -> Eat Breakfast -> Clean Dishes -> Put on tie -> Leave for work
Any delay in the completion of these nodes will mean that my departure time in the morning will be later than 7:35 am.
Those nodes which don’t lie on the critical path have a slack time greater than zero; this means that the start time for each of these nodes can be delayed by as much as the total slack time. For example, I can wait as much as ten minutes before brushing my teeth or ironing my shirt.
The critical path—and knowledge of slack times—is incredibly important when considering the scheduling of tasks, as well as the overall duration of a project. For example, I know that I can complete the entire project of waking up in the morning (provided the correct number of resources were available to complete some tasks concurrently) in 35 minutes. I also know that I can’t delay beginning working on any of the critical path parts of the project, or that 35 minutes will increase. Additionally, the knowing which nodes have slack time, and how much slack time they have, can tell me how long I can put off an element of a project (to accommodate available resources, for example).
There were a couple of caveats thrown into the explanation above, and if you were paying careful attention to the drawings, you’ll recognize why those caveats are important. The biggest was the statement, “provided the number of resources were available to complete some tasks concurrently.” This is a fundamental question, and obviously impacts the overall duration of the project in significant ways. One way to accommodate this is to adjust our PERT chart and critical path method to reflect available resources; while none of the initial nodes in our chart are dependent on each other, we might indicate that the early start times for each need to be delayed to reflect the fact that there’s only one of me to complete each of them. This would result in a lengthening of the critical path, and a lengthening of the whole project duration, of course, but would more accurately reflect how the project will actually be completed.
The combination of WBS, PERT chart and CPM provide an incredibly powerful approach to visualizing the scope, duration, and scheduling of a project. Next week, we’ll take a look at Gantt charts, which can take the whole thing to an entirely different level, and provide a (relatively) quick way to chart progress and react to the unexpected.
Tags:
Start Your FREE Subscription to Stage Directions Today!
SD covers everything from backstage to box office--performance to production and is filled with practical tips and information you need to stay on top of theatre trends.Start getting your own copy today!
Theatreface is the networking site for professional, educational and community theatre brought to you by Stage Directions Magazine.
© 2011 Created by Jacob Coakley.
You need to be a member of TheatreFace to add comments!
Join TheatreFace